Within the scope of the capacity expansion investment of the Kürekdağı Wind Power Plant (WPP) carried out by Bakır Enerji Elektrik Üretim A.Ş., which is 100% owned by our subsidiary Ağaoğlu Yenilenebilir Enerji Yatırım Holding A.Ş., the acceptance by the Republic of Türkiye Ministry of Energy and Natural Resources (MENR) for 3 of the 4 additional wind turbines was completed on November 6, 2025.
With this acceptance, an additional installed capacity of 17.7 MW has been added to Kürekdağı WPP. Following the acceptance process, the total installed capacity of Kürekdağı WPP has reached 53.7 MW.
In this context, the total installed capacity of the power plants managed under Tatlıpınar Elektrik Üretim A.Ş. has reached 339 MW.
Our Company continues to develop and commission renewable energy investments in line with its sustainable growth strategy.
Respectfully announced to the public.